An audit firm knew its jobs ran late but not why. I interviewed every role, mapped the whole workflow, and tested each problem against 2,500+ job records.
A job passed through seven teams, each with its own logs. Nobody had the whole picture of where the time went.
From recorded interviews to a reviewed, evidence-backed map.
Recorded sessions and walkthroughs with each role, plus written follow-ups over chat.
Two speech-to-text models on every recording; where they disagreed, both readings went back to the owner.
One page per process, lanes by department then job title, one action per box.
Manager comments tracked on the drawing with numbered tags and answered row by row.
Pain points checked against job logs, fee records and time reports. Counts only, no client data copied.
A generated website joins all pages, files and systems so anyone can follow a job across teams.
Median calendar days per stage, about 2,500 jobs in one year-end cycle.
Stages overlap, so they don't add up to 80.
of jobs started before the client confirmed the fee.
of jobs ran 30+ days late, most often for internal reasons.
signing pages changed hands about four times per job, on paper.
held the same dates for each job; one team re-keyed the other's weekly.
A script turns the drawings into a website where anyone can follow a job across teams. The demo uses a fictional firm.
Five root causes sit behind 9 problems.
Staff link Excel files by hand.
Between the audit team and central support.
The audit team owns it while the step waits on tax, head office or finance.
A standard case takes the same route as a difficult one.
Built one at a time, they don't pass data on.